The MetWest Alliance project involved the upgrade of the signalling, track and station infrastructure at No 1 Yard, Southern Cross Station. The Alliance delivered the project on time even though the schedule was compressed, within budget and with minimal disruption to train services while working in a high risk environment at one of Melbourne busiest live rail yards.
This paper aims to provide an overview of how an alliance works, the challenges faced at MetWest and to share insights on how delivery innovations were achieved which made the project successful.
|
|